Separator Review

Upload a datasheet, get a comment sheet with clause references.

An independent technical review of separator sizing and datasheets. Every comment has a severity, the calculation behind it, the clause it rests on and a recommended fix. Your senior reviewer signs off.

Runs in the browser · no install · free during beta

LAHHLAHNLLLALLALLoil / water interfaceK 0.118 > 0.098HOLDINLETGASWATEROIL

The problem

Every firm already pays senior hours to check separators.

A separator review means re-deriving K-values, retention times and level spacing from the datasheet and HMB, then writing it all up as a comment sheet. It is careful, repetitive work, and it lands on the people with the least time.

Separator Review does not compete with the designer's sizing tool. It checks the output, independently, and gives the reviewer every calculation to verify.

Sample output

A comment sheet your designer already knows how to answer.

V-1101 3-phase separator · Review comment sheet · Rev A

No.SectionCommentSeverityReferenceRecommendation
1Gas capacitySouders-Brown K = 0.118 m/s at max gas case vs 0.098 m/s allowable for wire mesh, derated for 62 barg.HoldGPSA Ch. 7; vendor dataIncrease ID or change to vane pack; confirm K with internals vendor.
2Liquid retentionOil retention 2.6 min vs 5.0 min required (24° API, foaming noted in basis).MajorAPI 12J; configured criteriaRaise NLL or extend T/T length; re-check level spacing.
3Inlet nozzleInlet ρv² = 7,200 Pa vs 6,000 Pa limit for vane-type inlet device.MajorNORSOK P-001; configured criteriaUpsize inlet 12" → 14" or specify cyclonic inlet device.
4Level settingsLAH to LAHH spacing 75 mm, below 100 mm minimum in configured criteria.MinorConfigured criteriaMove LAHH up 25 mm; verify against slug volume.
5Sour serviceH₂S partial pressure 0.9 kPa(a) exceeds 0.3 kPa(a) threshold; no sour note on datasheet.MinorNACE MR0175 / ISO 15156Add sour-service material requirement to datasheet notes.
6GeometryL/D = 3.8, within 3 to 6 band.InfoGPSA; good practiceNone.
Illustrative mock-up

Excel

Review comment sheet

The usual CRS layout: No., section, comment, severity (Hold, Major, Minor, Info), reference, recommendation, plus status and response columns for the designer.

PDF

Calculation note

Every check with inputs, equations, results and pass or fail, so the reviewer can verify each number.

PDF

Marked-up datasheet

Annotations on the original datasheet where the source was a PDF.

Checks and references (v1 rule pack)

Nine check areas. Every limit editable per client.

AreaCheckDefault basis (client override allowed)
Gas capacitySouders-Brown K vs allowable for the installed mist eliminator (mesh, vane, cyclone), derated at high pressureGPSA Ch. 7, API 12J, vendor data
Liquid retentionOil and water residence time vs required, driven by API gravity, foaming and emulsionAPI 12J, client spec
Level settingsLALL, LAL, NLL, LAH, LAHH spacing, hold-up and surge time, minimum level heightsClient spec, operator practice
Inlet nozzleInlet momentum (ρv²) vs inlet device limitNORSOK P-001 or client spec
Outlet nozzlesGas outlet momentum, liquid outlet velocity, vortex breakerClient spec
GeometryL/D ratio within typical band, droplet settling lengthGPSA, good practice
Slug handlingSlug volume fits between NLL and LAHHPIPESIM result or user input
Mechanical cross-checkDesign P/T margin over operating, PSV set point consistency, fire case notedAPI 521, client spec
Sour serviceH₂S partial pressure flag for material requirementsNACE MR0175 / ISO 15156

ignzai checks against your configured criteria. It does not claim compliance with any company or industry standard.

  • Engineer confirms every extracted value before checks run
  • Accept, edit or reject each comment before export
  • Every edit and rejection logged for audit

Demo

Datasheet to comment sheet in two minutes.

The 2-minute walkthrough is being recorded on a real 3-phase datasheet. Join early access and we will send it to you, or book a live walkthrough.

Get early access

FAQ

Does it claim compliance with my company's standards?
No. Separator Review checks against your configured criteria. Default limits come from public references (GPSA, API, NORSOK, NACE) and live in an editable rule pack per client. Your reviewer decides what is compliant.
How are PDF datasheets read?
An extraction model reads the datasheet into a structured form. You see the PDF and the extracted fields side by side and confirm every value before any check runs. Nothing is assumed silently.
Can I edit or reject a comment?
Yes. The reviewer accepts, edits or rejects each comment before export. Edits and rejections are logged, and with your consent they tune your rule pack.
What process data does it need?
Gas, oil and water flows, densities, viscosities and Z-factor, from your heat and material balance (Excel or HYSYS export) or typed in. Slug volume from a PIPESIM study and PSV data are optional.
Does it design the separator?
No. It reviews a design, it does not replace the designer's tool. Full sizing optimisation, internals vendor selection and mechanical thickness calculations are out of scope for v1.
Which vessels are covered?
Two- and three-phase separators, horizontal and vertical. Scrubbers and knock-out drums use the same engine and are next on the roadmap.

Send us a datasheet you have already reviewed.

See whether ignzai catches the same Hold and Major comments. Free during the 90-day beta.